Builder charging 20% extra - normal?
Is it normal for a builder to charge 20% extra for preliminaries / time/ admin /supervision etc? It amounts to about 3600, of which 600 ish covers toilet hire and trips to the tip. He has bought and arranged delivery of most materials, but I have also done some.
All his other prices on the invoice are reasonable and accounted for in my own estimated figures. He is VAT registered so the 20% VAT is also accountable.
He is a good reputable builder but the additional 20% for admin etc seems quite steep, especially as I've done a lot of the ground work for our project. Is this normal?
4 Answers from MyBuilder Conversion Specialists
Best Answer
MB joinery and building maintenance
Nottingham•Member since 1 Jul 2020•No feedback yet
If it is a big building company then it's to be expected,but if its a one or two man outfit then it's abit steep.
Answered 1st Jul 2020
Mareham Le Fen•Member since 1 Mar 2009•83jobs,100%positivefeedback
somebody has to pay for his time fuel, ect only a fool works for nothing.
2020年7月2日回答
Regency conservatory roofs ltd
Thornton Cleveleys•Member since 3 Feb 2020•No feedback yet
You don’t pay 1 penny more than what is written on the quote
Answered 1st Jul 2020
Diss•Member since 13 Jul 2020•32jobs,100%positivefeedback
Charging an extra % is standard. This allows for any wastage and minor hiccups on the way.
A builders final price should have already accounted for toilet hire and tip trips. If these come to more than the builder has allowed for, then unless there have been any deviations from the original quote it’s bad estimation on the builders part.
Answered 14th Jul 2020
Related Questions
- builder is charging extra money!
My builder has agreed to renovate our house in £60,000, but now he keeps on demanding us for money. we have paid him 80% of the...
- The builder says the renderer is now charging him more money and wants us to pay.
We are 15 weeks into a quoted 8 week build. The builder and I signed a contract stating a fixed amount for work to be...
- My Builder is charging us £14k extra
Hi We hired a builder to do a loft conversion on ur two bed house and he quoted us £50k and there was a payment schedule in...
- Builder has presented a huge extra bill
Hi We have just had a major renovation and extension of our house and have spent over £250,000 with the builder. He has stuck...
Post your job to find high quality tradespeople and get free quotes
Question Categories
- All Questions
- Architectural Services
- Bathroom Fitting
- Bricklaying
- Carpentry & Joinery
- Carpet & Lino
- Central Heating
- Chimneys & Fireplaces
- Conservatories
- Conversions - General
- Damp Proofing
- Demolition & Waste Clearance
- Driveways
- Electrical
- Extensions
- 筋膜,索夫its & Guttering
- Fencing
- Gas Work
- Groundwork & Foundations
- Handyman
- Hard Flooring
- Insulation
- Kitchen Fitting
- Landscape Gardening
- Locksmiths
- Loft Conversions
- New Builds
- Painting & Decorating
- Plastering
- Plumbing
- Restoration & Refurbishment
- Roofing
- Security Systems
- Stonemasonry
- Tiling
- Tree Surgery
- Windows